The National Geodetic Survey posted the results of their local tie survey at the NSGN Haleakala site on Maui, Hawaii. Vectors were measured between the SLR and GNSS station and ground marks to support the International Terrestrial Reference Frame and NGS's Foundation CORS program. The survey results, report, and SINEX file are available at the NGS website.
A winter storm damaged commercial power transmission lines to the observatories on Haleakala, Hawaii, USA on February 10, 2019. Commercial power to TLRS-4 at Haleakala has been restored.
A winter storm damaged commercial power transmission lines to the observatories on Haleakala, Hawaii, USA. Since February 10, TLRS-4 has been without power.
The local electric power company estimates repair to take a minimum of 4 weeks and as long as 8 weeks. The team is exploring ways to power the site with a backup generator or by connecting to a nearby observatory that has backup power.