April 22, 2019 Progress on the shelter and arrival of the dome parts at GGAO 04/22/2019 The shelter continues to progress. The doors and windows are taking shape and the roof is being worked. The sea container with the dome parts arrived at the port of Baltimore from Germany on April 15th and was delivered to GGAO the morning of April 18th. There was a great deal of excitement at GGAO when it arrived and a lot of the site construction and SGSLR teams were there to greet it. A large forklift was required to remove it from the truck as it weighs over 5000 lbs. It is currently resting just North of NGSLR, waiting for the Baader team to arrive and assemble the parts and then install the dome on the shelter. The shelter under construction The freight container with the dome parts